The first set of assessment files  submitted  were incomplete - However, in view of wanting to see the heat map I had approved 10 out of 15 files that were submitted last week.

In order that the revised files be updated again  it was necessary to "Unapprove" (send the approved file back in to the left side folder), by clicking on the X option on the rightmost side.
If we do not do this, the assessor receives a message stating "the file cannot be uploaded as it has already been approved".

Once the file is "unapproved",  each assessor is able to   upload his revised file and for the manager to receive the updated file. The date of the file apload appears on right side of the table  in the "Pending Approval " List as a verification.  

The new files need to be approved again  as next step. 

Participants

Réponses(1)

Aucune réponse n'a été donnée à cette publication pour l'instant
  1. il y a 6 ans
Accepter la solution
Thanks Kshem, will make a note of this in the EVM2 user guides. Just to confirm: an assessor cannot upload a questionnaire if it has already been approved. If an assessor wants to upload an updated version of the approved questionnaire, the manager must first UNAPPROVE the questionnaire. Once this has been done, the assessor can upload the updated questionnaire (note that this will OVERWRITE the previously approved questionnaire). The manager can then review & approve the updated questionnaire.